(→Hubs) |
|||
Line 25: | Line 25: | ||
* 6 x 5-way rings | * 6 x 5-way rings | ||
* 15 x 4-way rings | * 15 x 4-way rings | ||
=== Construction of full scale ziptie hub prototype === | |||
<gallery> | |||
File:Hub 1.jpg|Take 75mm ring with 24mm drilled holes, 40mm inner hub ring, strut and ziptie. | |||
File:Hub 3.jpg|Ziptie ring in 8mm drilled holes. | |||
File:Hub 8.jpg|Continue as above. | |||
File:Hub 10.jpg|Make sure to leave ~5mm on the ziptie when cutting short so the catch cannot slip so easily. | |||
</gallery> | |||
== Fasteners == | == Fasteners == |
Revision as of 09:41, 30 June 2015
Maxidome | |
---|---|
Participants | |
Skills | construction, grinding, drilling |
Status | Active |
Niche | Mechanics |
Purpose | Infrastructure |
Tool | No |
Location | |
Cost | |
Tool category |
Maxidome Property "Tool Image" (as page type) with input value "File:" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process.
{{#if:No | [[Tool Owner::{{{ProjectParticipants}}} | }} {{#if:No | [[Tool Cost:: | }}
Frame construction
Tubing
- 30 x 'S' : 1.57m x 22mm steel
- 40 x 'M' : 1.82m x 22mm steel
- 50 x 'L' : 1.86m x 22mm steel
Hubs
- 46x 40mm steel ring
- 25 x 6-way rings
- 6 x 5-way rings
- 15 x 4-way rings
Construction of full scale ziptie hub prototype
Fasteners
- 7 mm wide zipties
- Grommets
- Tent rope
Cover construction
Container construction
We need one or more containers to be able to transport the dome in. Before we can build a container we need to figure out what the optimal design would be. A wooden crate? Multiple wooden crates? Plastic bag? Duffelbag? Plz help think
Design decisions
- The dome will be 9m in diameter
- The tubes will be 22m steel tubes
- The inner ring of the hub will be a 40mm external diameter steel ring, with a height of 25 mm.
- The outer ring of the hub will be a 75mm external diameter PVC ring, with a height of 50mm.
- Both ends of a steel pipe will be equipped with a 8mm hole, with it's centerpoint located 8mm from the edge.
- The outer hub will be equipped with 24mm holes.
TODO
Frame construction
- Acquire missing tools needed
Settle on sizeSettle on tube diameterSettle on hub design- Determine total length of tubing required
- Find supply of steel tubing
- Design hubcap
- Print hubcaps
- Purchase tubes
- Select zipties
- Purchase zipties
- Cut tubes to required lengths
- Drill tube ends so zipties can be fitted
- Create assembly plan
- Assemble in back yard
- Settle on container solution
Cover construction
Request a sample of hermetix from supplier- Validate Hermetix as viable covering candidate.
- Decide on covering material
- Find supply of covering material
- Extract required shapes from material
Decide on how to bind the shapes together- Create cool showoffy idiopolis artsy design for covering
- Find the appropriate grommets to mount in the cover in order to rope the covering down (10 mm? 20 mm?)
- Determine how many grommets are needed
- Order grommets
- Order grommet fastening tool, if the one we have does not fit
- Order special tape like fabric to strengthen the joint between the cover and the grommet
- Calculate how much rope we need
- Order rope
Find a method to cut holes in the fabric in order the mount the rivets
Container construction
- Settle on container type
- Design containers?
- Build containers