Electricity overhaul | |
---|---|
Participants | Septillion |
Skills | |
Status | In progress |
Niche | Electronics |
Purpose | Infra |
Tool | No |
Location | Space |
Cost | |
Tool category | Infra |
Electricity overhaul Property "Tool Image" (as page type) with input value "File:{{{Picture}}}" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. {{{Picture}}} {{#if:No | [[Tool Owner::{{{ProjectParticipants}}} | }} {{#if:No | [[Tool Cost::{{{Cost}}} | }}
This page is to make some investigate and track the changes that could/need to be done or are done, keeping in mind that we also would like Solar power.
This page is only for the project itself, see the pages about the distribution board and power distribution.
Stuff that needs to happen
Replace the current groepenkast- Rebuild whole infra
- Add more groups
- Remove old infra
- upgrade aansluiting
Ideas
What do we like to achieve in the end:
- One distribution board for the whole space @ grid connection point
- RCBO (Dutch: aardlekautomaat) for every end circuit to isolate circuits for each other.
- Replace all wiring
- New wiring in central cable tray along the length of the space
- Go step by step, old distribution stays in place until room is remodeled
- Upgrade to 3-phase power
Original layout
Original circuits
Called "groepen" in Dutch.
Groepen kast A
Name | Location | Description |
---|---|---|
Groep 4 Kast A | Toilet groep bar | 16 A |
Groep 5 res. | ||
3 fase groep | voeding kast b | 3x 20A afgezekerd. |
Groepen Kast B
Name | Location | Description |
---|---|---|
Groep 1 | zaal 3 zaal2 gang 1 wcd | 16 A |
Groep 2 res. | Zaal 2 zaal3 1 wcd, gang deur makershoek zaal 1 studio | |
groep 3 | zaal 3 bar makershoek |
New
Circuits
Name | Location | Description | |
---|---|---|---|
light incl. emergency light. | whole space. | 1 | |
serverrack. | hall. | 2 | |
Cv. installation. | cv. closet. | 3 | |
Dishwasher. refrigerator incl. beer. | bar. | 4 | |
Cooker | bar. | 6 | |
Furness | 2X16A or 3x16A | 7 | |
General Usage | bar. | 8 | |
room1. | room 1. | 9 | |
room 1 | room1. | 10 | |
room 2 | 11 | ||
room 2 | 12 | ||
room 3 | room 3. | 13 | |
room 3 | room 3. | 14 | |
Maker corner 1 | maker corner. | 15 | |
Solar panels | rooftop | 16 | What is nessary (Rubberduck has 2X16 A for it) |
3-phase power
Currently the space is supplied with 1-phase power. It is a 1x30A (or maybe even a 1x25A) connection. Now the distribution board is upgraded and has a 4-pole main switch (Dutch: hoofdschakelaar) it is possible to apply for an upgrade to 3-phase. This would mean an upgrade to 3x25A. The monthly fee is the same as the current 1-phase.
The upgrade needs to be applied from Liander via [1]. The cost is €332,15 and is expected tot take 6 weeks. The smart meter will get replaced in the process.
Old ideas
Just moved here for reference.