Volkshuis onderhoud: Difference between revisions
No edit summary |
m (→Zaal 2) |
||
| (38 intermediate revisions by 5 users not shown) | |||
| Line 1: | Line 1: | ||
Please collect here all the things you think are requiring maintenance soonish. | |||
Todo list: [[Media:BIJN-MJOP_bouwkundig_rapport_2021.pdf|Bouwkundig raport]] | |||
Budget: [[Media:BIJN-MJOP_begroting_2021.pdf|Bouwkundige begroting]] | |||
{{Project | {{Project | ||
|Name=Volkshuis onderhoud | |Name=Volkshuis onderhoud | ||
| Line 8: | Line 14: | ||
|Category=Infra | |Category=Infra | ||
}} | }} | ||
* | |||
* Possible wasp nest on side were sign used to be | = Ongoing Issues = | ||
== Bar == | |||
* Ventilation isn't operated by HASS and uses a bit excessive power, replace? | |||
== Outside == | |||
* Possible wasp nest on side were sign used to be (corner zaal 3) | |||
* Doorframe of frontdoor needs love/replacement | |||
* Almost -all- outside windowframes are rotted or rotting | |||
== Toilet == | |||
* Toilet is leaking between the reservoir and the bowl | |||
* Toiletreservoir is not attached to wall | * Toiletreservoir is not attached to wall | ||
* | |||
== Zaal 1 == | |||
* Roof leaking above the couch? | |||
* <s>Maybe make Airco in zaal1 a permanent installation?</s> | |||
= Ceiling Renovations = | |||
== Todo == | |||
=== Materiaal === | |||
* isolatie - iig genoeg tot+met rookruimte | |||
* folie - bijna op! | |||
* aluminium tape - bijna op! | |||
* tacker nietjes - iig genoeg tot+met keuken | |||
* raggels - ruim genoeg tot+met rookruimte/keuken | |||
* schroeven raggels - ruim genoeg | |||
* gips platen - ruim genoeg tot+met keuken | |||
* schroeven gips - ruim genoeg | |||
* plafond-gaten-vul-spullie - bijna op! | |||
* lijstwerk - iig genoeg tot+met rookruimte | |||
* slagschroeven lijstwerk - ruim genoeg | |||
* purschuim - ruim genoeg | |||
=== Zaal 2 === | |||
* <s>kabelgoot soldeerhoek</s> | |||
* <s>gipsplaten aanbrengen</s> | |||
* <s>lijstwerk en purschuim aanbrengen</s> | |||
* Schakelaar + stopcontact aanleggen x2 - WIP (50%) | |||
* Gaten en schroeven plafond wegwerken (welk spullie nodig?) | |||
* <s>Kozijnen raam kant afwerken</s> | |||
* <s>Bevestiging gordijn-rails uitzoeken/aanbrengen</s> | |||
=== Gang === | |||
* <s>rest isolatie en folie aanbrengen</s> | |||
* <s>gipsplaten aanbrengen</s> | |||
* lijstwerk en purschuim aanbrengen | |||
=== WC === | |||
* <s>ventilatie gat in het dak vrij maken</s> | |||
* lijstwerk en purschuim aanbrengen - WIP | |||
* <s>rest isolatie en folie aanbrengen</s> | |||
* <s>rest gipsplaten aanbrengen</s> | |||
* <s>Stopkraan urinoir plaatsen</s> | |||
* <s>Drukspoeler urinoir vervangen</s> | |||
* <s>rest plafond en oude latten verwijderen</s> | |||
=== Rookruimte === | |||
Afbouw: | |||
* <s>oud plafond verwijderen</s> | |||
* <s>interne deurpost en raam rookruimte verwijderen</s> | |||
* <s>wasbak rookruimte verwijderen</s> | |||
* <s>water en afvoer rookruimte ontkoppelen</s> | |||
Opbouw: | |||
* <s>isolatie en folie aanbrengen</s> | |||
* <s>gipsplaten aanbrengen</s> | |||
* lijstwerk en purschuim aanbrengen | |||
* randen lijstwerk afkitten | |||
=== Keuken === | |||
* oud plafond verwijderen - WIP | |||
* isolatie en folie aanbrengen | |||
* gipsplaten aanbrengen | |||
* lijstwerk en purschuim aanbrengen | |||
=== Power Infra === | |||
* Kabelgoten doortrekken tot zaal 1 | |||
* Stroom Zaal 1 permanenter fixen (nu temp via kabelgoot ipv wckabels) | |||
* Stroom NOC meer secure | |||
== Todo: hierna == | |||
=== Zaal 2 === | |||
* makerhoek inrichten - WIP | |||
* <s>electrohoek inrichten</s> | |||
=== Rookruimte === | |||
* upgrade ventilatie | |||
* upgrade inrichting | |||
* upgrade entertainment | |||
=== Keuken === | |||
* alle stroom anders | |||
* nieuwe/betere kastjes? | |||
* nieuw kook-eiland? | |||
* betere (koffie/bier) bar? | |||
* upgrade entertainment? | |||
=== Oude Makerhoek === | |||
* leeg halen ... | |||
* plafond vervangen ... | |||
=== Zaal 1 === | |||
* ... | |||
= Whole Building = | |||
=== Replace radiator knobs === | |||
Replace all radiatorknobs with wax engines on HASS operated relays. | |||
=== Replace all power infra === | |||
The BOM has been ordered.[[:File:order bevestiging 1402117.pdf]] | |||
We have planned a 300mm wide cable guide from room 3 into room 1, so along the full length of the Space. Further we have planned a 70mm wide guide in room 3, perpendicular to the main guide. Also for room 2 we have planned a 70mm guide parallel to the main guide on the centerline of room 2. It is connected to the main guide with the same 70mm guide planned over the second door into room 2 (the one that is permanenty closed). The guides will hang from the beams with threaded rods (M10). Fixture of the threaded rods to the beams is tbd. | |||
=== Replace all ceiling material === | |||
All the soft boards need to be removed including the wood lattice. | |||
We should have a flat roof now with the beams visible and nothing else. So you are looking directly at the inside of the roof (particle board). | |||
The steps to install the new ceiling are as follows: | |||
# Put the rolls of stone wool in between the beams. The beams are approx. 40cm apart and the rolls are 40cm wide, so it should fit. If not just wedge an extra sliver of stone wool in. | |||
# Tack moisture dampening foil directly on the beams. seal it with the roll of aluminium tape, so there are no holes. | |||
# Screw the lattice work/slats (Dutch: rachels) perpendicular to the beams directly on the beams. hart to hart distance between the "rachels" is 60cm. Notice that the slats will not be level in all directions, but will follow the slope of the roof, because they are attached to the beams. | |||
# screw the plasterboard to the slats at a 90 degree angle. The seam of two subsequent boards in a row should not coincide with the seam in the preceding row. | |||
` | |||
Latest revision as of 12:08, 28 November 2025
Please collect here all the things you think are requiring maintenance soonish.
Todo list: Bouwkundig raport
Budget: Bouwkundige begroting
| Volkshuis onderhoud | |
|---|---|
| Participants | Berend |
| Skills | |
| Status | Active as fuck |
| Niche | Building maintenance |
| Purpose | Repair and renovation |
| Tool | No |
| Location | |
| Cost | |
| Tool category | Infra |
Ed & Willem Bever 1.png {{#if:No | [[Tool Owner::{{{ProjectParticipants}}} | }} {{#if:No | [[Tool Cost::{{{Cost}}} | }}
Ongoing Issues
Bar
- Ventilation isn't operated by HASS and uses a bit excessive power, replace?
Outside
- Possible wasp nest on side were sign used to be (corner zaal 3)
- Doorframe of frontdoor needs love/replacement
- Almost -all- outside windowframes are rotted or rotting
Toilet
- Toilet is leaking between the reservoir and the bowl
- Toiletreservoir is not attached to wall
Zaal 1
- Roof leaking above the couch?
Maybe make Airco in zaal1 a permanent installation?
Ceiling Renovations
Todo
Materiaal
- isolatie - iig genoeg tot+met rookruimte
- folie - bijna op!
- aluminium tape - bijna op!
- tacker nietjes - iig genoeg tot+met keuken
- raggels - ruim genoeg tot+met rookruimte/keuken
- schroeven raggels - ruim genoeg
- gips platen - ruim genoeg tot+met keuken
- schroeven gips - ruim genoeg
- plafond-gaten-vul-spullie - bijna op!
- lijstwerk - iig genoeg tot+met rookruimte
- slagschroeven lijstwerk - ruim genoeg
- purschuim - ruim genoeg
Zaal 2
kabelgoot soldeerhoekgipsplaten aanbrengenlijstwerk en purschuim aanbrengen- Schakelaar + stopcontact aanleggen x2 - WIP (50%)
- Gaten en schroeven plafond wegwerken (welk spullie nodig?)
Kozijnen raam kant afwerkenBevestiging gordijn-rails uitzoeken/aanbrengen
Gang
rest isolatie en folie aanbrengengipsplaten aanbrengen- lijstwerk en purschuim aanbrengen
WC
ventilatie gat in het dak vrij maken- lijstwerk en purschuim aanbrengen - WIP
rest isolatie en folie aanbrengenrest gipsplaten aanbrengenStopkraan urinoir plaatsenDrukspoeler urinoir vervangenrest plafond en oude latten verwijderen
Rookruimte
Afbouw:
oud plafond verwijdereninterne deurpost en raam rookruimte verwijderenwasbak rookruimte verwijderenwater en afvoer rookruimte ontkoppelen
Opbouw:
isolatie en folie aanbrengengipsplaten aanbrengen- lijstwerk en purschuim aanbrengen
- randen lijstwerk afkitten
Keuken
- oud plafond verwijderen - WIP
- isolatie en folie aanbrengen
- gipsplaten aanbrengen
- lijstwerk en purschuim aanbrengen
Power Infra
- Kabelgoten doortrekken tot zaal 1
- Stroom Zaal 1 permanenter fixen (nu temp via kabelgoot ipv wckabels)
- Stroom NOC meer secure
Todo: hierna
Zaal 2
- makerhoek inrichten - WIP
electrohoek inrichten
Rookruimte
- upgrade ventilatie
- upgrade inrichting
- upgrade entertainment
Keuken
- alle stroom anders
- nieuwe/betere kastjes?
- nieuw kook-eiland?
- betere (koffie/bier) bar?
- upgrade entertainment?
Oude Makerhoek
- leeg halen ...
- plafond vervangen ...
Zaal 1
- ...
Whole Building
Replace radiator knobs
Replace all radiatorknobs with wax engines on HASS operated relays.
Replace all power infra
The BOM has been ordered.File:order bevestiging 1402117.pdf
We have planned a 300mm wide cable guide from room 3 into room 1, so along the full length of the Space. Further we have planned a 70mm wide guide in room 3, perpendicular to the main guide. Also for room 2 we have planned a 70mm guide parallel to the main guide on the centerline of room 2. It is connected to the main guide with the same 70mm guide planned over the second door into room 2 (the one that is permanenty closed). The guides will hang from the beams with threaded rods (M10). Fixture of the threaded rods to the beams is tbd.
Replace all ceiling material
All the soft boards need to be removed including the wood lattice.
We should have a flat roof now with the beams visible and nothing else. So you are looking directly at the inside of the roof (particle board).
The steps to install the new ceiling are as follows:
- Put the rolls of stone wool in between the beams. The beams are approx. 40cm apart and the rolls are 40cm wide, so it should fit. If not just wedge an extra sliver of stone wool in.
- Tack moisture dampening foil directly on the beams. seal it with the roll of aluminium tape, so there are no holes.
- Screw the lattice work/slats (Dutch: rachels) perpendicular to the beams directly on the beams. hart to hart distance between the "rachels" is 60cm. Notice that the slats will not be level in all directions, but will follow the slope of the roof, because they are attached to the beams.
- screw the plasterboard to the slats at a 90 degree angle. The seam of two subsequent boards in a row should not coincide with the seam in the preceding row.
`